2. Early Participant Testing (EPT)
2.1 Onboarding Process
The following document provides a diagrammatic view of the onboarding process from an LFI and TPP perspective.
2.2 Mercury Execute KYC/KYB Process with LFIs
Mercury will review the onboarding form and execute the KYC/KYB processes with the LFIs Primary Business Contact (PBC).
The KYC/KYB processes are a pre-requisite for LFIs and therefore they must complete this process before being onboarded onto the Open Finance Portal (OFP).
At the end of this process, the PBC will be authorised on the Open Finance Trust Framework (OFTF) to issue the Open Finance Terms & Conditions for the LFI representatives to sign.
Once the LFIs PBC is onboarded on the OFTF, they must appoint the LFI representatives who will sign the Participation Document.
Mercury will then validate signatures and that the appointed representatives have enough powers to represent the Participant.
2.
...
3 OFTF Sandbox Available to Industry
Once the PBC is authorised on the OFTF, they will be sent an e-mail from the OFTF Sandbox asking to register on the platform and proceed with the generation of the T&Cs.
Having undertaken the process in 3.1, the PBC will be promoted on the OFTF Sandbox, allowing them to register additional technical users, who will also be asked to register on the platform.
Technical users will be now able to create/manage technical resources responsible for generation of necessary transport, signing and encryption certificates.
2.
...
4 OFTF Production Available to Industry
The Same PBC promoted on the OFTF Sandbox will be given administrative powers on the OFTF Production allowing them to execute the same steps defined on 3.2.
...
A series of engagement sessions will take place from to .
The sessions will be held weekly for a duration of 3 hours and held from 10:00am - 1:00pm GST. However the first session on will be 2 hours in duration.
The sessions will be technically focused and should be attended by the LFI’s technical teams.
The agenda for each session can be found in the expandable section below.
LFI attendance is mandatory for the first 5 sessions.
...
title | Engagement Session Details |
---|
...
Session / Date
...
Topics
...
Consortium Lead
...
Audience
...
ES1:
...
Introductions: 10:05am - 10:10am
Overview engagement sessions.
Overview of the API Hub User Guide: 10:10am - 10:40am
OFP Overview: 10:40am - 11:10am
OFTF Directories (Sandbox & Production).
OFTF Certificate issuance & key rotation.
Ozone API HUB.
Implementation Milestones and Timelines: 11:10am - 11:50
Q&A Session: 11:50am - 12:00pm
...
Ozone
Raidiam
...
Tier 1 LFIs.
...
ES2:
...
Recap and updates - 10:00am - 10:15am
Ozone API Hub Infrastructure integration - 10:15am - 11:00am
Network Diagram.
Connectivity Requirements & Guides.
API Hub Functional Integration - 11:00am - 11:45am
CSR generation & certificate signing.
Sequence Diagrams.
Consent Manager / Authorisation server API Standards.
Authorisation UI requirements.
Ozone Connect Standards.
Break - 11:45am - 12:00pm
Q&A Session - 12:00pm - 1:00pm
Clarification on standards.
Clarification on integration process.
OFTF Onboarding process (TBC).
KYC / KYB process - 10:15am - 10:45am
...
Ozone.
...
Tier 1 LFIs.
...
ES3:
...
Recap and updates - 10:00am - 10:15am
Testing approach - 10:15am - 11:15am
Development time testing
Postman collection and setup.
Ozone Connect test automation tool.
FCS test automation tool.
UAT test cycle.
Admin Portal - 11:15am - 11:45am
User guide.
Reporting.
Break - 11:45am - 12:00pm
Log shipping - 12:00pm - 12:30pm
Application logs.
Infrastructure logs.
Q&A Session - 12:30 - 1:00pm
Clarification on standards.
Clarification on integration process.
...
Ozone.
...
Tier 1 LFIs.
...
ES4:
...
Recap and updates - 10:00am - 10:30am
Q&A Session - 10:30am - 1:00pm
Clarification on standards.
Clarification on integration process.
...
Ozone.
...
Tier 1 LFIs.
...
ES5:
...
Recap and updates - 10:00am - 10:30am
Q&A Session - 10:30am - 1:00pm (Break 11:45am - 12:00pm)
Clarification on standards.
Clarification on integration process.
...
Ozone.
...
Tier 1 LFIs.
...
ES6:
...
Recap and updates - 10:00am - 10:30am
Updates on API implementation guide.
Q&A Session remainder - 10:30am - 1:00pm (Break 11:45am - 12:00pm)
Clarification on standards.
Clarification on integration process.
...
Ozone.
...
Tier 1 LFIs.
The agenda for each session will be published here.
3.1 Ozone Bilateral Technical Working sessions
...
Ozone / LFI to establish and test connectivity for the pre-production environment.
Ozone / LFI to test the integration for the pre-production environment.
LFI to perform functional testing in the pre-production environment.
A postman collection will be available to test the end-to-end journeys
The Ozone Test Suite will be available to test the LFI's Ozone Connect implementation
LFI to provide pre-production sign off.
...
LFI to perform functional testing in the pre-production environment.
A postman collection will be available to test the end-to-end journeys
The Ozone Test Suite will be available to test the LFI's Ozone Connect implementation
LFI to provide pre-production sign off.
...
LFI to perform functional testing in the pre- production environment.
Ozone to perform penetration testing and remediation.
LFI to provide production sign off.
...