Author

Chris Michael David Plews Isla Humphreys

Version

1.0

Classification

DRAFT

1. Introduction

This page intends to provide a summary of high level milestones and detailed steps for onboarding LFIs onto the Open Finance Platform (OFP).

2. Early Participant Testing (EPT)

Screenshot 2024-06-27 at 17.43.32.png

2.1 Mercury Execute KYC/KYB Process with LFIs

2.2 OFTF Sandbox Available to Industry

2.3 OFTF Production Available to Industry

3. LFI Engagement Sessions

Session / Date

Topics

Consortium Lead

Audience

ES1:

Introductions - 10:00am - 10:15am

  • Overview engagement sessions.

  • Milestones and Timelines.

  • API Hub User Guide.

KYC / KYB process - 10:15am - 10:45am

OFP Overview 10:45am - 11:15am

  • OFTF Directories (Sandbox & Production).

  • OFTF Onboarding process.

  • OFTF Certificate issuance & key rotation.

  • Ozone API HUB.

Q&A Session 11:15am - 12:00pm

  • Clarification on standards.

  • Clarification on integration process.

  • Ozone.

  • Mercury.

  • Strategy&.

  • Raidiam.

Tier 1 LFIs.

ES2:

Recap and updates - 10:00am - 10:15am

Ozone API Hub Infrastructure integration - 10:15am - 11:00am

  • Network Diagram.

  • Connectivity Requirements & Guides.

API Hub Functional Integration - 11:00am - 11:45am

  • CSR generation & certificate signing.

  • Sequence Diagrams.

  • Consent Manager / Authorisation server API Standards.

  • Authorisation UI requirements.

  • Ozone Connect Standards.

Break - 11:45am - 12:00pm

Q&A Session - 12:00pm - 1:00pm

  • Clarification on standards.

  • Clarification on integration process.

  • Ozone.

Tier 1 LFIs.

ES3:

Recap and updates - 10:00am - 10:15am

Testing approach - 10:15am - 11:15am

  • Development time testing

    • Postman collection and setup.

    • Ozone Connect test automation tool.

    • FCS test automation tool.

  • UAT test cycle.

Admin Portal - 11:15am - 11:45am

  • User guide.

  • Reporting.

Break - 11:45am - 12:00pm

Log shipping - 12:00pm - 12:30pm

  • Application logs.

  • Infrastructure logs.

Q&A Session - 12:30 - 1:00pm

  • Clarification on standards.

  • Clarification on integration process.

  • Ozone.

Tier 1 LFIs.

ES4:

Recap and updates - 10:00am - 10:30am

Q&A Session - 10:30am - 1:00pm

  • Clarification on standards.

  • Clarification on integration process.

  • Ozone.

Tier 1 LFIs.

ES5:

Recap and updates - 10:00am - 10:30am

Q&A Session - 10:30am - 1:00pm (Break 11:45am - 12:00pm)

  • Clarification on standards.

  • Clarification on integration process.

  • Ozone.

Tier 1 LFIs.

ES6:

Recap and updates - 10:00am - 10:30am

  • Updates on API implementation guide.

Q&A Session remainder - 10:30am - 1:00pm (Break 11:45am - 12:00pm)

  • Clarification on standards.

  • Clarification on integration process.

  • Ozone.

Tier 1 LFIs.

3.1 Ozone Bilateral Technical Working sessions

Session Date

Session Timing (GST)

LFI

12:30pm - 2:00pm

Abu Dhabi Commercial Bank (ADCBAEAA)

3:00pm - 4:30pm

Emirates NBD (EBILAEAD)

12:30pm - 2:00pm

First Abu Dhabi Bank (NBADAEAA)

3:00pm - 4:30pm

Dubai Islamic Bank (DUIBAEAD)

12:30pm - 2:00pm

Mashreq (BOMLAEAD)

3:00pm - 4:30pm

Abu Dhabi Industrial Bank (ABDIAEAD)

12:30pm - 2:00pm

HSBC Bank Middle East Limited (BBMEAEAD)

3:00pm - 4:30pm

Commercial Bank of Dubai (CBDUAEAD)

4. T1 LFI Onboarding

Screenshot 2024-06-27 at 17.44.44.png

4.1 LFI Implementation Activities

4.1.1 Development of Ozone Connect and Modified Authentication Journeys

4.1.2 LFI Pre-Production Deployment

4.1.2 LFI Production Deployment

4.2 Joint Activities

4.2.1 Pre-Production Readiness

By the end of this milestone, the following items need to be achieved:-

  1. Number of environments identified.

  2. Domain names and well-known endpoints identified.

  3. Authorisation servers onboarded onto OFTF Sandbox.

  4. Certificates generated.

4.2.2 Onboarding Questionnaire

4.2.3 LFI-OFP Pre-Production Integration [DC3]

During this period, the following activities need to be achieved:-

  1. Ozone / LFI to establish and test connectivity for the pre-production environment.

  2. Ozone / LFI to test the integration for the pre-production environment.

  3. LFI to perform functional testing in the pre-production environment.

  4. LFI to provide pre-production sign off.

4.2.4 LFI-OFP Pre-Production Integration [DC4]

By the end the DC4 pre-production integration period, the following activities need to be achieved:-

  1. LFI to perform functional testing in the pre-production environment.

  2. LFI to provide pre-production sign off.

4.2.5 Production Readiness

By the end of this milestone, the following items need to be achieved by LFIs:-

  1. Domain names and well-known endpoints identified.

  2. Authorisation servers onboarded onto OFTF Directory.

  3. Certificates generated.

4.2.6 LFI-OFP Production Integration [DC3]

By the end the DC3 production integration period, the following activities need to be achieved:-

  1. Ozone / LFI to establish and test connectivity for the production environment.

  2. Ozone / LFI to test the integration for the production environment.

  3. LFI to perform functional testing in the production environment.

  4. Ozone to perform penetration testing and remediation.

  5. LFI to provide production sign off.

4.2.7 LFI-OFP Production Integration [DC4]

By the end the DC4 production integration period, the following activities need to be achieved:-

  1. LFI to perform functional testing in the pre-production environment.

  2. Ozone to perform penetration testing and remediation.

  3. LFI to provide production sign off.

5. Ozone Deployment Cycles

5.1 DC3 Ozone Sandbox Deployment

By the end of the DC3 Ozone Sandbox deployment, the following activities will be achieved:-

  1. Deploy Release xxx into sandbox environment.

  2. Sandbox environment acceptance testing (internal).

  3. FAPI Certification of Sandbox.

  4. Sandbox go-live.

5.2 DC3 Ozone Pre-Production Deployment

By the end of the DC3 Ozone Pre-production deployment, the following activities will be achieved:-

  1. Generate CSRs for certificates from LFIs.

  2. Receive certificates from LFIs.

  3. Deploy into pre-production environment.

  4. Internal testing in pre-production.

5.3 DC3 Ozone Production Deployment

By the end of the DC3 Ozone production deployment, the following activities will be achieved:-

  1. Generate CSRs for certificates from LFIs.

  2. Receive certificates from LFIs.

  3. Deploy into production environment.

  4. Internal testing in production.

5.4 DC4 Ozone Sandbox Deployment

By the end of the DC4 Ozone Sandbox deployment, the following activities will be achieved:-

  1. Deploy Release xxx into sandbox environment.

  2. Sandbox environment acceptance testing (internal).

  3. FAPI re-certification.

  4. Sandbox go-live.

5.5 DC4 Ozone Pre-Production Deployment

By the end of the DC4 Ozone Pre-Production deployment, the following activities will be achieved:-

  1. Deploy release xxx into pre-production environment.

  2. Internal testing in pre-production.

5.6 DC4 Ozone Production Deployment

By the end of the DC4 Ozone Production deployment, the following activities will be achieved:-

  1. Deploy release xxx into production environment.

  2. Internal testing in production.

6. Implementation Checklist

The following checklist aims to provide high level steps that need to be completed throughout the implementation process.

Item

Owner

Status

Comments

Complete KYC/KYB process

Mercury / LFI

Complete Prerequisites Questionnaire (Via JSD form)

LFI

LFI Onboard to OFTF Sandbox

LFI

LFI Onboard to OFTF Production

LFI

LFI Development

LFI Ozone Connect Development

LFI

LFI Authorisation Flow Development

LFI

Pre-Production Readiness

Complete pre-Production Configuration Questionnaire (Via JSD Form)

LFI / Ozone

Generate Pre-Production certificates on OFTF Sandbox

LFI / Ozone

Deploy Ozone Connect and Auth Flow Development into Pre-Production

LFI

Pre-Production Connectivity Verification

LFI / Ozone

DC3 Pre-Production Integration and Testing

LFI

DC3 Pre-Production Sign Off

LFI

DC4 Pre-Production Integration and Testing

LFI

DC4 Pre-Production Sign Off

LFI

Production Readiness

Complete Production Configuration Questionnaire (Via JSD Form)

LFI / Ozone

Generate Production Certificates on OFTF Sandbox

LFI / Ozone

Deploy Ozone Connect and Auth Flow Development into Production

LFI

Production Connectivity Verification

LFI / Ozone

DC3 Production Integration and Testing

LFI

DC3 Production Penetration Testing and Remediation

Ozone

DC3 Production Sign Off

LFI

DC4 Production Integration and Testing

LFI

DC4 Production Penetration Testing and Remediation

Ozone

DC4 Production Sign Off

LFI